Enel signs for 317 MWdc of South Carolina solar. What does the $255 million measure?

The buyer disclosed an expected balance-sheet impact. The seller disclosed who will manage construction. Together, those details explain how to read the deal.

Illustrative photograph of rows of tilted solar trackers at Nellis Air Force Base in Nevada.

What did Enel agree to buy?

On 20 November 2026, Enel announced an agreement to acquire 100% of a South Carolina solar portfolio from energyRe. The projects total 317 megawatts of direct-current capacity (MWdc). The companies expect closing in the first quarter of 2027, subject to approvals. Enel specifically identifies US antitrust and foreign-investment clearances. [1]

There is a second handover to track after the ownership change. In its own release, energyRe says it will manage construction through commercial operation. A portfolio sale can therefore transfer ownership on one date while responsibility for delivering the completed plants continues under another agreement. [2]

Three figures with different meanings
Disclosed figureWhat it describes
317 MWdcSolar capacity covered by the agreement
About $255 millionExpected impact on Enel’s group net financial debt after completion and entry into service
About $30 millionEstimated annual EBITDA once the plants are operating

Source: Enel’s acquisition announcement. The forecasts describe the operating portfolio. [1]

Why the headline numbers cannot establish a transaction multiple

Enel expects about $255 million of impact on group net financial debt after completion and entry into service. Its estimate of about $30 million of annual EBITDA also applies once the plants are operating. Enel forecasts average annual production above 540 GWh. All three figures describe a future operating position. [1]

A buyer comparing bids would first need the equity consideration, any project debt taken on or retired, and spending still required to reach operation. Those components are absent from the announcement. Dividing the disclosed debt impact by forecast EBITDA would produce a number whose numerator has a different meaning from enterprise value.

Which portfolio was financed in October?

On 12 October, energyRe announced an $815 million financing package for five South Carolina projects totalling approximately 360 MW. The November releases describe 317 MWdc and do not reconcile the project lists. The earlier announcement also gives its capacity figure simply in MW. Establishing which sites and facilities overlap requires an asset-by-asset schedule and consistent capacity units. [1] [2] [3]

What should an owner request before handover?

REN analysis. Ask for the remaining cost and completion date for each site, alongside the party responsible for delays, contractor claims and the testing needed to start revenue. Then trace a single delayed site through the portfolio forecast. Which construction payment still falls due? Which revenue moves into the next quarter? Which lender consent or reserve release depends on that site passing its test?

This produces a more useful comparison for an investment committee than a headline price per megawatt. It shows how much capital changes hands at closing, how much remains at risk during construction, and when the operating portfolio can start supporting distributions.

Sources

  1. Enel · acquisition announcement, 20 November 2026 (PDF)
  2. energyRe · seller’s announcement, 20 November 2026, via PR Newswire
  3. energyRe · five-project financing announcement, 12 October 2026, via PR Newswire

Illustrative photograph. Solar trackers at Nellis Air Force Base, Nevada by U.S. Air Force. Cropped and converted to WebP. Public domain in the United States.

Suggest a correction · Editorial standards