Hornsea 3’s £3.5 billion transmission tender puts a price on availability

Ofgem opened a competition to own the cables and substations connecting Hornsea 3 to shore. For a bidder, the financial question is how long repairs could take when a fault occurs at sea.

Adapted from Renewable Energy Network research dated . The analysis reflects the information available on that date.

Aerial view of transformers, overhead lines and switchgear at a substation near Bayfield, Colorado.

At a glance

The licence ties revenue to the availability and performance of the transmission equipment. Before pricing the bid, test who pays for a cable fault, who can mobilise a repair vessel and how much revenue is exposed while the link is unavailable.

What was Ofgem putting out to tender?

On 21 October, Ofgem opened its 14th Offshore Transmission Owner tender round. Investors would compete to buy and operate the transmission assets connecting Hornsea 3 to Britain’s grid. Ofgem estimated the round at around £3.5 billion. [1] Ofgem assesses the transfer value of the assets. Bidders specify the revenue they require to own and operate them. [2]

The assets include cables and offshore and onshore substations. The developer builds them and sells them to the successful bidder, which receives a transmission licence. Ofgem described an inflation-linked revenue stream running for up to 25 years, subject to how reliably the assets are available and how they perform. [1]

How does an outage reach the financial model?

Consider a fault on an export cable. The operator first needs to locate the fault. A repair may then depend on a suitable vessel, compatible spare cable, specialist crew and a weather window. A replacement part in a warehouse solves only one of those problems.

Ask the technical team to estimate a plausible repair duration. Have the commercial team apply the licence’s availability provisions to that same outage, then compare the projected revenue reduction and repair costs with the timing of any insurance recovery. That exercise gives lenders a basis for sizing liquidity and helps bidders judge the value of reserving repair capacity in advance.

At handover, request the cable test results, defect list and warranty terms together. A warranty can allocate repair costs to a contractor while the transmission owner is still carrying the consequences of an unavailable link.

Sources

  1. Ofgem · Hornsea 3 offshore transmission tender launch, 21 October 2026